LG
April 6, 2005
Status of
Prototype Ladder Development
We report on the status of the prototype ladder development
with reference to the plan developed late last year and linked here. http://www.lbnl.leog.org/Pixel_Prototype_Testing.pdf
We have constructed 3 prototype ladders. The original
intention was to construct one prototype with a set of staged additions
cumulating in a finished prototype. This turned out to be not easily possible
with the existing mechanical fixtures for detector placement. The fixtures, as
constructed, is adequate for doing an accurate placement of 10 detectors but
not well suited to placing individual detectors in the correct position. This
led to the creation of prototype #1 which had 9 detectors placed on the
prototype cable mounted on a RVC/CFC beam. We ran into problems troubleshooting
9 bonded detectors so another prototype was constructed and in-house
wire-bonding capability was acquired. An additional prototype was constructed
to allow 2 people to work independently.
Prototype Ladder Status
We now have 3 prototype ladders.
Ladder 1 –
Construction – CFC/RVC/CFC carrier, cable, 9 x 50 µm MIMOSA5
detectors, 3 detectors (all 4 sectors) instrumented with amplifiers and
differential drivers.
Status – This prototype was damaged during construction and
3 of the MIMOSA5 detectors are chipped or cracked. The MIMOSA5 detector in
position 8 (2nd detector from the right) returns ROWMK. The rest are
not yet tested fully and the board needs modification of the wire bonding and
surface mount electronics to be tested further.
Ladder 2 –
Construction – CFC/RVC/CFC carrier, cable, 3 x 50 µm MIMOSA5
detectors, 2 detectors (all 4 sectors) instrumented with amplifiers and
differential drivers.
Status – This prototype is the one that we are using to read
multiple detectors out over the cable and into the motherboard / ADC-memory
daughter card. The MIMOSA5 detectors in positions 10 and 8 are wire bonded and
instrumented with drivers. The detectors are yellow graded chips and each has 2
working sectors.
Ladder 3 –
Construction – bakelite carrier, cable, 1 x 50 µm MIMOSA5
detector, 1 detector (all 4 sectors) instrumented with amplifiers and
differential drivers.
Status – This prototype is the one that we first
successfully read out over the cable and into the motherboard / ADC-memory
daughter card. The MIMOSA5 detector in position 10 is wire bonded and instrumented
with drivers. The detector is graded green but has only 2 working sectors. The
other sectors are damaged somehow and draw a large amount of current. Some data
was taken before the bond wires to that sector melted.
Motherboard and ADC/memory Daughter Card Status
We have constructed 1 motherboard and 2 daughter cards. Some
layout errors were discovered and patched around with the result that the
system is now functional but not as easily reconfigurable due to the necessary
patching. We are taking data read out from the card through a LVDS connection to
a custom PCI card in a LINUX PC. The functional schematic is shown below.
Development on the CDS in VHDL on the daughter cards in
ongoing. We will post links to the data soon.
Status of Prototype Ladder Testing With Respect to the
Testing Plan
From the previously linked document we have the following
testing goals with the status.
Stage 1 – prototype goals
- Cable
performance with 1 detector – This has been successfully tested and the
performance, while not yet quantified, appears to be the same as with the
testing done with a MIMOSA bonded to our single chip mezzanine card.
- Mechanical
assembly with 1 detector / bonding – This has been successfully
accomplished.
Stage 2 – prototype goals
- Cable
performance with multiple detectors. – This is currently under
investigation and will be quantified. Initial results look good.
- New MB
performance - This is currently under investigation and will be
quantified. Initial results look good. We are testing the MB, daughter
card and overall system performance and will be reporting on it as soon as
results are generated.
- New
daughter card performance – See above.
- VHDL
CDS performance – This is under development. We will post results as they
are generated.
- Overall
system performance – See above.
- Mechanical
assembly with multiple detectors / bonding. – The mechanical assembly done
uncovered some needed additional precautions in handling and identified
new fixturing that will need to be constructed
for producing individual MIMOSA prototypes. For producing finished ladders,
the fixturing is appropriate.
- Alignment
techniques. – The alignment techniques tested through the fixturing seem quite good. Some additional mechanical
model ladders were construcred with red graded
MIMOSA chips and some of the alignments and mechanical properties checked.
A first look can be found here. http://www.lbnl.leog.org/crossing_lines_measurement_first_look.htm
- Cooling
system design and performance. – This has not yet been examined. We will
do these tests with the mechanical model ladders.
- Beam test?
– not yet.
Lessons Learned and Current Questions
- Handling
– The CFC/RVC carriers with their 50 µm MIMOSA detectors are actually
quite fragile. During the construction of the 1st prototype
ladder, the ladder was dropped as it was removed from a pressure chamber
used to properly fix the film adhesive. The small fall (~10cm) broke at
least 3 of the Detectors and damaged the carrier. We will be developing
improved handling techniques that help keep this type of accident from
happening.
- Fixturing – The fixturing
used for producing the 9 MIMOSA prototype and the
mechanical model ladders worked well. The fixtures were not designed,
however, for individual installation of MIMOSAs
into an existing array. This should not have been necessary in out
original plan but became necessary as we ran out of usable working MIMOSAs to install and had to install and place by
hand. New fixturing will be designed and
manufactured if we need to add more detectors to the existing ladders.
- Orcad MIMOSA5 chip definition – The Orcad definition of the pad layout on the chip that
was used to produce the cable has an error. This required that we change
the wire bonds. Fortunately the error only required an offset of 1 pad for
8 wire bonds. This error will be corrected.
- gain adjustments – We have optimized the gain in a
particular MIMOSA to match the ADC that we are using. Testing some other
bonded detectors, we find that the gain is
somewhat off for these chips. We will keep looking for an optimized
compromise for all, or apply individual gain settings to each chip.
- ROWMK
– Only 1 chip output such as ROWMK may be attached to the output bus. Any unpowered MIMOSA (or even powered ones, in our
experience) will keep the buss pulled down.
- Reference
Voltages – The chip reference voltages are currently being set to 2.5V with
a resistor divider consisting of 2 5K ohm resistors. The input impedance
of the voltage reference inputs is significantly low with respect to the
5K resistors used. In addition, the input impedance seems to vary between
chips so some of our reference voltages are not what we would like. There
is some evidence that the impedance is also dependant on what is happening
in the chip. We need to study this further and possibly add a buffer to
keep this input stable and at the correct voltage.
- Motherboard
Layout – An error was made in the layout of the motherboard that resulted
in the mirror imaging on the daughter card sockets. Since most of the
signals are differential, we were able to adapt without heroic efforts but
this and a few other errors need to be corrected. This will make it hard
to do a complete 5 daughter card test without making a new motherboard. We
will correct this.